Press
Releases
Comments
by Sahabat Alam Malaysia and the Consumers Association of Penang
on the detailed EIA of: JKR proposed proposed raw water transfer
project from Pahang to Selangor by MAB, August 2000
I. INTRODUCTION
The EIA for
the proposed project has been undertaken in view of the requirements
under Section 34A of the Environmental Quality Act 1974 and the
EIA Order of 1987 for water supply projects. The project is initiated
by the Government of Malaysia.
Following the
display of the Detailed EIA [ DE ] for public viewing and comments,
we are pleased to submit our comments and feedback, as presented
below.
The justification
given for this project is that demand for treated and piped water
in Selangor and Kuala Lumpur will exceed current supply capacity
of 3250 million litres per day (MLD) by 2003. Phase lll of the Sg.
Selangor project will add a further 1,100 MLD allowing capacity
to support projected demand until about 2007. The consequences of
failure to meet demand after that time are compared with the economic
loss and social unrest that came with the 1998 water crisis.
This project
is supposed to ensure that supply meets projected demand until 2017.
The project proposes to:
1. Build two
earthfill dams in Pahang:
 |
on the Sg. Kelau, reservoir 4,090 ha. - 10 km NE of Bentong;
and |
 |
on the Sg. Telemong, reservoir 1,532 ha. - 1 km south of Karak. |
2. A water intake
on the Sg. Kelau with 11 km of pipeline.
3. A weir on
the Sg. Bentong with 7 km of pipeline.
4. A 37.5 or
45 km water transfer tunnel with inlet 1.5 km south of Karak that
goes beneath the Main Range and has
an outlet about 3 km downstream of Pekan Ulu Langat.
This project would be undertaken in 3 phases and
is expected to take about 11 years to complete.
It is pertinent
to note that the EIA legal requirements cover only the construction
of dams or impounding reservoirs and not the transfer tunnel, pipelines
or filtration plants and sludge ponds. This EIA study discusses
the tunnel and pipelines, but not the filtration plants or sludge
ponds.
The Pahang State Government has stated that the dam sites above
are not required for their own water needs by 2050, and so available
for use in the Klang Valley. It can thus be argued that these dams
would have no function without the transfer tunnel. Together with
any new filtration plant, the tunnel should be considered an integral
part of the project as a whole.
The DE raises many critical issues of concern as follows -
II. CHANGES
IN PROJECT DESIGN REQUIRE NEW EIA
The DE addresses
impacts that will arise as a result of the project as set out above
- viz. that involving the construction of both the Kelau and Telemong
dams, the Kelau intake, the Bentong Weir, the transfer tunnel and
the pipelines.
Since the submission
of the DE, we understand that there have been various changes to
the project design such as the shelving of the Telemong Dam, changes
to the Kelau intake and the Bentong Weir. According to press reports,
the Pahang State Government has recommended that the Telemong dam
be shelved due to 'sensitivities'.
We welcome the
decision of the Pahang State Government in this regard, and call
for a review of the entire project including the Kelau Dam, the
tunnels and the pipelines, since the environmental and social costs
of the project are still grave and significant.
Moreover, we
are not convinced that the project can be justified given the huge
costs involved and the social and environmental trade-offs that
have to be made when other better alternatives to supply water have
not been adequately dealt with.
The proposed
changes to the project design are not minor but are indeed substantial
and major. A redesign of the project concept must necessarily involve
the conduct and submission of a new EIA. A substantial change in
the project design such as the shelving of the Telemong Dam would
mean that the impacts as originally envisaged would be different,
depending on the scale, location and changes to the original project
design.
In the circumstances,
we submit that a completely new Detailed EIA ought to be submitted,
taking into account the new changes to the project design. Of particular
importance is the impact of the revised project on the existing
river systems and water flows.
Further, given
that there are changes to the project design, it is imperative that
public feedback is sought on the new EIA to be done, instead of
soliciting comments on the present DE which is misleading.
Hence, we reiterate
the need for a new Detailed EIA to be commissioned, based on the
revised project design so as to ensure that the public is given
a true and fair account of what is at stake.
III. SERIOUS
DISCREPANCIES
There are some
very major discrepancies in the DE in relation to the water demand
projections.
In chapter 1
pg. 6, the DE states that Phase III of the Sungei Selangor scheme
which is now under construction and will be completed by 2002 will
boost supply capacity to 4,350 MLD from the current reliable yield
of 3,250 MLD. It further states that "This is only sufficient
to meet demands up to the end of 2004 after which other sources
need to be in place to avoid the water shortage in the Klang Valley."
However, in
the Executive Summary of the DE, it is stated that the Phase III
of Sungei Selangor will be sufficient to meet demands "
up to the end of 2007."
When we refer
to Figure 1.6 on the 'Water Demand and Supply Balance', the conclusion
in the Executive Summary appears to be more accurate.
Such a glaring
error right in the beginning of the DE reveals shoddy work and a
lack of professionalism.
Other areas
of discrepancy further undermine the credibility of the DE.
The DE is rather
confusing as to what exactly the water yields will be from the proposed
project. In chapter 2 at pg 14, the DE states that at the initial
stage of operation, the average yield is 1043 MLD, derived from
the Kelau dam and the Kelau intake. At the final stage, the DE says
that an average yield of 886 MLD will be obtained from these sources.
Firstly, there
is no explanation provided as to why the yield will drop between
the initial stage of operation and the final stage. Secondly, exactly
how these figures have been obtained remains a mystery.
The figures
in Table 1.8 which show the increment of reliable yields by the
project do not tally with the figures stated in chapter 2. If we
adopt the figures in that table, the water yield from the Kelau
dam and the intake should be 968 MLD [ 432 + 536 ] and not 1043
MLD.
The same is
the case for the figures in relation to the Telemong Dam and the
Bentong Weir. In chapter 2 at pg 14, the DE states that the yield
from these sources would be 1455 MLD. This conclusion cannot be
derived from the figures in Table 1.8. If we adopt the figures in
Table 1.8, then the total yield from the Telemong Dam and the Bentong
Weir should be 1132 MLD [ 665 + 467 ].
The total reliable
yield from the entire project in Table 1.8 is 2,100 MLD. If we follow
the text in chapter 2 pg 14, the total average yield from the entire
project would be 2,321
[ 866 + 1455 ] MLD - more than 221 MLD than what is projected in
Table 1.8.
Why the discrepancy
in the figures? This has to be explained.
IV. NO JUSTIFICATION
FOR THE PROJECT
The present
project is justified on the basis that the demand for water supply
in Selangor/Kl will exceed the current supply capacity of 3,250
MLD by 2003. The supply from the ongoing Sungei Selangor Dam is
expected to be an additional 1,100 MLD [making it total of 4,350
MLD], which is estimated to meet the water demand up till about
the end of 2007.
According to
the figures in Table 1.8, the total increment in reliable yield
derived from the entire project would be 2100 MLD. With the shelving
of the Telemong dam, based on the figures in Table 1.8, the total
increment in reliable yield would be 1,435 MLD, without any alteration
to the Bentong Weir.
With this additional
supply, the total amount of water supply available for Selangor/KL
will be 5,785 MLD. According to the water demand projections set
out in Table 1.1 of the DE, in the year 2005, the demand is 4270
MLD and in 2010, it is 5,850 MLD. Therefore, assuming that these
figures are correct, the revised project [ without the Telemong
dam ] will not be able to meet water demands beyond 2010.
According to
Table 1.9, the timing of the commissioning of the Kelau intake for
the planned demand would be 2006 and for the Kelau dam and the intake
would be 2008. Given the water demand projections, within a matter
of two years since 2008, the water demand needs would have outstripped
the supply potential of the revised project.
Even if we took into account the entire project, inclusive of the
Telemong dam, the total supply of 6450 MLD would only be realised
in stage 3 of the project, ie. in the year 2013. According to the
water demand projections in Table 1.1, by 2015, some 8014 MLD would
be needed. Again, this shows that the supply potential of the entire
project would be grossly inadequate to meet the water demand within
two years of the commissioning of this entire project.
The DE estimates
the overall project cost to be more than RM 3 billion and this figure
has not taken into account the financing costs of the investment.
[ see chapter 15 pg.3 ]. With the shelving of the Telemong dam,
we are not certain what the project cost will be. In any case, it
is safe to presume that the construction of the 45 km tunnel to
transfer the water would constitute a significant part of the project
cost.
In the light
of the above, given the huge financial costs involved, there appears
no sufficient justification whatsoever to carry on with either the
original project or the revised one which will have only a very
short-term 'benefit' before alternative sources of water supply
have to be sourced. Why sink in such a huge sum of money for so
short a duration? A more prudent approach would be to look for better
alternatives which will meet the water demand needs in the long-run.
The Statement
of Need in chapter 1 is grossly inadequate, as it has failed to
deal with the issues stated in the preceding paragraphs. The need
for the project has not been sufficiently justified from an economic
standpoint. Investing so much money on a project with no long-term
benefit defies economic sense and prudence.
What ought to
have been seriously and comprehensively dealt with are possible
alternatives to meeting the water demand for Selangor/KL.
Support for our conclusions can also be drawn from chap 15 of the
DE which deals with the Benefit Cost Analysis.
At pg 3, the
DE states that there are other alternatives to this project that
should also be considered. The Consultants recommend that "
The costs of undertaking these alternatives must then be weighed
against the total costs of the Project." It further states
that " Without a more detailed information, the benefits and
costs of the project cannot be squarely quantified. It is therefore
proposed that a more detailed study at a later stage be carried
out
The high investment cost alone justifies that alternatives
must be looked at before a decision is finally made"
V. ALTERNATIVES
NOT PROPERLY CONSIDERED
Despite recognising
the need to consider alternatives before making a final decision
as stated in the DE above, the consideration of these options in
chapter 2 is grossly inadequate, highly deficient and superficial.
Under chapter
2, in relation to the 'No Build Option' and the 'Non-Dam Alternatives',
the DE states that the "Alternatives to the proposed project
have been identified and thoroughly evaluated for environmental
impact". [ see chapter 2, pg 19 ]. This statement is grossly
misleading, as there has been no thorough evaluation of the alternatives
to the proposed project.
Moreover, the
conclusions in chapter 15 itself as alluded to above, contradict
this claim as it recommends more detailed studies on the alternatives
before a final decision is made. The Benefit Cost Analysis does
not support the conclusion that the proposed project is the only
option.
From the foregoing
analysis, it is clear that the DE itself in relation to the justification
for the project is contradictory - the conclusions in chapter 1
under Statement of Need and in chapter 2 on the No Build Option
are not supported by the recommendations in chapter 15 on the Benefit
Cost Analysis.
One of the options
that was alluded to in the DE was the direct water intake of raw
water from several large rivers in other states, requiring the construction
of long distance pipelines. The DE refers to the need for feasibility
and detailed studies. Without the conduct of one, the DE itself
states that no conclusion on this can be derived. [ see chapter
2 pg. 15 ].
Since this option
has not been properly studied, the DE cannot dismiss this option
as one that is not viable. The DE states in a very cursory fashion
that the cost of such a venture could be close to RM 2 billion.
How this conclusion was arrived at is yet another mystery.
This only proves
the point that the DE is not objective and biased in favour of the
proposed project as the only viable option.
Alternatives
such as using ground water reserves in Selangor, water from outside
the Klang Valley from the Sg. Bernam or the Sg. Sepang or effective
water conservation and recycling are dismissed as requiring further
investigation or EIA work that would cause excessive delay. The
only options discussed as being viable are the building dams with
full supply levels (FSL) of 87.5m or 90m. The DE is indeed highly
biased.
VI. PROJECT
OPTIONS
It is pertinent
to note that in the consideration of viable options for water supply,
the DE should have been more comprehensive in its approach. The
proposal by a non-governmental group called the 'Concerned for Sg.
Selangor' which was submitted to the DOE in relation to the Selangor
Dam project ought to have been seriously and rigorously considered.
A copy of the
proposal is attached herewith. In summary, the proposal is for the
intake of raw water from the Perak River, with pipelines that can
follow the existing railway track at a very low cost of only RM
741 million or from Lake Kenyir. These proposals should not be dismissed
as being without merit, when no opportunity has been provided to
consider them seriously.
In page 15 of Chapter 2 of the DE, it is stated that the water transfer
arrangement would involve laying of long distance pipelines which
would be subject to potential leakages, sabotage, crossing of private
lands, roads and forest areas, aesthetics and no net positive residual
impact. The proposed water transfer from Pahang to Selangor also
involves laying of long distance pipelines and tunneling. Are these
pipelines entirely free from leakages, sabotage, etc? The DE report
should have given fair coverage of all the options available and
not be biased.
The most viable
and practical option is to use existing lakes or dams to supply
water to Klang Valley by using water pipelines following existing
corridors such as roads, railway lines or the gas pipelines. Two
sources of water supply are considered viable: water from Sungai
Perak or water from Kenyir Lake in Terengganu.
Water Transfer
from Sungai Perak
Perak has considerable
water storage capabilities in the 15,000ha Temenggor Dam and other
existing dams on the Perak River. A study in the early 1990s indicated
that a minimum of 500million litres per day (mld) supply from the
Perak River can be used for interstate water transfer or for export.
Given the size of the Sungai Perak basin it is likely that more
than 1000mld can be supplied.
The options
are as follows:
1. Construction
of a water intake station at or near Kampung Gajah, which is a small
town next to the Sungai Perak and is above the salt water intrusion
line. Pipelines would then have to be laid along road reserves to
Tapah Road where it enters railway property and follow the railway
line to Rasa in Selangor. Depending on the circumstances, it can
either be discharged directly into the Sungai Selangor at the Rasa
area or diverted into Sungai Tinggi, which already has an impounding
dam under Phase 2 of the Selangor water supply plan.
The approximate
distance from Kampung Gajah to Sungai Selangor is about 130km and
the piping diameter would be 213cm, which is considered sufficient
to handle 1.1billion litres per day without any problems. The volume
can be increased or decreased by regulating the turbines.
The whole system
includes an intake station at the riverbank with heavy particle
settlement tanks, an outlet reservoir at the discharge point, a
filter system to screen out particles above 5mm, a settlement reservoir
with about 100,000 litres holding capacity along the way, pumping
stations along the way, and pipes of mild steel with bitumen outer
coating and concrete lining. The whole cost would amount to about
RM740million.
2. Another option
would be to place the water intake station further north at Parit
and piped to the railway line at Batu Gajah.
3. A better
way to move water is by gravity feed, where water is first pumped
to higher ground and allowed to drain downwards for a long distance.
This scenario entails that it would be possible to start intake
at Chenderoh Dam. As Chenderoh Dam is shallow, water would have
to be released from Temenggor Dam to keep feeding the lower dam.
From here, the engineers can determine the method of flow, of which
the smoother route would be to use the railway lines. Train routes
are always gradual in gradient change.
Water Transfer
from Terengganu
The water storage
capacity of the Kenyir Dam is so large (37,000ha) that water extraction
for a pipeline will not have a major impact on the dam itself. Based
on a previous study, extraction of 1,000mld of water would drop
about 1.5m of water level in the dam per year, insignificant considering
he large area of catchment and the large amount of rainfall for
inland Terengganu.
Additionally,
the availability of water from the Kenyir Dam is not a problem.
The State Government in fact has no objection to supplying the water
to other states provided that the developer pay for the annual premium/royalty
to the state and bear the cost of pipeline construction.
1. A contractor
has quoted Petronas a cost of RM 400million to deliver water to
Dungun from Kenyir dam. With this in mind, we can assume that the
pipeline corridor has been established and secured.
2. There is
also an existing Petronas gas pipeline extending from Kertih to
Gemas and north to the west coast. There will be a 30km stretch
from Dungun to Kertih that requires a pipeline corridor, which can
be constructed along road reserves. Evidently, there is now a clear
water line route from Kenyir to Selangor.
Waterpipes do
not require wide spaces and they are able to utilize the narrow
corridor route of the gas pipelines.
3. Otherwise,
an alternative route would be to follow a newly constructed road
from Kenyir Lake to Gua Musang and from there to connect to the
railway track to Gemas and on to Selangor.
Rain water
harvesting
The option and
possibility of rainwater harvesting systems for the individual residence
should be contemplated. The water collected would be filtered and
automatically pumped to a gravity tank for cleaning purposes, which
is a major source of household water consumption.
Localized
water sources
Small, localized
sources of ground and surface water should be identified and collected
to serve the immediate vicinity and local communities. This would
reduce the need for larger water resource and distribution facilities
while utilizing the retention capacity of existing wetlands and
natural underground aquifers.
Polluted streams,
rivers and lakes can be rehabilitated and revived as water supply
sources for irrigation and industry.
Appropriate
water pricing policy
A review of
the existing water tariffs should be carried out and a fair pricing
system based on an appropriate scale should be adopted to encourage
water saving. This would reduce the demand for water.
Reduce water
losses
The State Government
in collaboration with the municipal council and JKR would have to
begin extensive repair works of all the leaks in the system, tightening
the theft problem and would have to eventually change all the asbestos
piping in the city to long lasting pipes.
Wise use
of water in the agricultural sector
In the agriculture
sector, wise water use can be promoted through the development of
more efficient irrigation practices, establishment of a cost-recovery
mechanism, development of conservation incentives, consolidation
of irregular and small landholdings, and through recycling water.
VII. ENVIRONMENTAL
ISSUES
1. Biodiversity
Concerns
1.1 Both the
floral and faunal investigations compiled partial name lists of
species present.
Most effort
was concentrated on timber species, and vertebrate animals, ignoring
the bulk of taxa that make up biological diversity. It was noted
that no rare or endemic species were found, thus implying that the
site haS little conservation value. No attempt was made to
interpret:
 |
the role species play in the local ecosystem; |
 |
the significance of the local populations for conservation of
genetic diversity; |
 |
the contribution the site makes for migration and the movement
of genetic material; |
 |
describe the habitats; |
 |
describe associations among and between plants and animals;
etc. |
Name lists alone
cannot adequately describe the biology of a site, interpret the role
they play in local ecology and thus understand what impacts will arise
from the loss of the habitats and the inundation of the sites. Because
no attempt was made to qualify the interaction between the animal
communities currently resident on the sites proposed for flooding
and neighbouring areas, no model can be made to project impacts that
could occur once the populations in the proposed reservoir sites have
been eliminated. This is a failure of the DE to address a TOR - impacts
on biological diversity.
1.2 The faunal
study examined the single issue of impacts from the removal of existing
wildlife, with emphasis on large mammals. The recommendation given
was that animals should be driven into neighbouring forest areas
or captured and transferred to ex-situ locations. What was not addressed
include:
 |
Whether habitat space was available for the displaced animals
in neighbouring forest? |
 |
Whether cage space, keeper, adequate skills and upkeep resources
were available or being prepared in the ex-situ transfer sites
recommended? |
 |
What was to become of wildlife that could not be driven? |
 |
Why licenced/controlled harvesting was not examined as an option
for clearance? |
These are points
where the DE has not adequately examined the feasibility of its recommendations.
1.3 The EIA
warns of the potential negative publicity that could arise should
large vertebrates be marooned on islands by the rising floodwaters.
This happened on the much larger Kenyir dam site, requiring an expensive
exercise to evacuate elephants from small islands. In this particular
case there are no elephants recorded on the sites. (The EIA does
not make clear what species were actually observed as resident or
recorded from interviews and reports with local people.) And a crude
evaluation of the species list given suggests that the marooned
animal problems could be limited to primates, small felids and possibly
bear.
The DE recommended
an animal rescue task force be mobilised on a large scale. Though
maintaining this functional capability in government agencies may
be important on a national scale, it may not be the best use of
resources available for biological diversity for this project.
We are concerned
that concentrating discussion on high-cost animal rescue operations
will ignore less news-making requirements to minimise biodiversity
loss. The DE should emphasise that a Species Management Plan would
be required for the clearance/construction phase to minimise impacts
on biodiversity at the landscape, taxa and genetic level.
1.4 The DE recommended
the destruction of vegetation on islands in the reservoir area.
This would result in unnecessary loss of habitat space. The reason
given was to prevent large mammals becoming trapped. This recommendation
is concerned with animal welfare alone. This is a social issue and
does not contribute to the conservation of biological diversity.
The DE ought to have concluded as follows:-
 |
all recommendations in the DE for the destruction of forest
on islands be ignored, and that all areas above the flood zone
be marked on the ground, and neither logged or cleared; |
 |
instead of clearing the forest on islands, forested corridors
be left along the hill ridges to dry high ground to allow marooned
species to move to higher ground; and that |
 |
the islands should be allowed to reach their natural species
equilibrium through species loss rather than through the much
slower process of secondary succession.
|
1.5 Biomass removal
has been included in the DE together with biodiversity issues.
We submit that
this item has been misplaced, regarding biomass removal as an issue
of waste management and thus an engineering matter. We are concerned
that by grouping biomass removal with 'soft' issues of biodiversity
- issues that are usually undervalued by the EIA process through
a lack of information, the EIA is attempting to endorse the avoidance
of disposal costs.
Biomass removal
ought to be treated as a part of waste management. (See further
discussion below in this regard).
1.6. Floral/forestry
issues.
The assessment
of flora and forestry aspects is limited to a 1ha plot and the information
from this plot has been the basis for biodiversity assessment.
We submit that:
 |
The sampling strategy used in the floral study is inadequate
to generate information necessary for biodiversity studies. |
 |
The studies should have been based on a number of smaller plots
distributed on a stratified approach.
|
 |
A stratified inventory is necessary to determine the maximum
timber extraction rates (biomass removal) and thus work out
stumpage value. |
 |
Inadequate sampling has produced unrealistic biomass values
which is unsupported by any know referenced literature.
|
 |
A
forest harvesting plan to minimise erosion risk hazards ought
to have been developed.
|
2. Quarrying,
waste material disposal and biomass removal
Taking an engineer's
perspective, the DE has described what should be routine practices
for waste management from construction sites. It has not adequately
examined the wastes peculiar to this particular project. These would
include wastes from:
 |
about
1.2 million cu.m. of tunnel wastes
|
 |
earth
quarries used for dam construction materials;
|
 |
washing
sands used in construction and
|
 |
a
biomass of about 500,000 tons.
|
If the DE had adequately addressed these issues, it would have:
 |
described the wastes,
|
 |
estimated
the amounts,
|
 |
described
how these wastes would reach an equilibrium state with the
environment;
|
 |
described
how escaping materials would have been transported, their
target media and impacts.
|
be practical alternatives far cheaper than incineration and far more
acceptable than open burning
The DE study
should have discussed the impacts and trade-offs that would arise
if residual biomass were:
It would have then
examined options for waste management and made recommendations for
the options that would have been most appropriate for the scale impacts
and resources of the project.
(a) Voluminous Spoil Material
The DE estimates
in most parts that the length of the tunnel is 45 km with a diameter
of 5.2 metres. Calculations show that the tunnel borrowing will
generate spoil material to the tune of 1.2 million cubic metres!
To dump such a large volume of spoil, we estimate that a landfill
which is about 1km long, 100 m wide with a height of 10 m would
be required to contain all that material. At a 10 m height, 24 acres
of land would be required!
The DE states
that only 300,000 tonnes of aggregates will be generated from the
tunnel construction. Exactly how this figure was arrived yet is
not disclosed but given the tunnel specifications, it appears that
this figure is a gross underestimate and must be challenged.
One major omission
of the DE is its failure to address this issue adequately. All the
DE states is the areas to keep the spoil material have been identified
but exactly where they are and what size they will be have not been
dealt with.
The disposal of such a large volume of spoil material is indeed a
major environmental issue which had not been sufficiently addressed
in the DE. On this score alone, the DE is seriously flawed.
(b) Quarried
Material
In the case
of quarried material, that taken from sites within the reservoir
area that would later be flooded, requires mechanisms to minimise
siltation to local river systems. For other sites outside the flood
areas, the DE should describe the usual quarrying practices which
would apply as well as recommend methods that would ensure landscaping
and revegetation after quarry closure is actually implemented.
(c) Sand Washing
The practice
of sand washing usually causes stream siltation. The DE should describe
the steps needed to minimise impacts of silt to local waterways.
(d) Biomass removal
Under para 12.7.8,
the DE mentions preparation of a waste management plan, but this
does not make reference to biomass removal. The DE gives a biomass
of 2.238x 106 tonnes of biomass for removal from the Kelau site.
This we feel is a gross overestimate. We urgently suggest that this
reference be consulted: Kato, R.,Y.Tadaki and H.Ogawa. 1978.
Plant biomass and growth increment studies in Pasoh Forest. Malayan
Nature Journal 30(2): 211-224.
The biomass values ought to be re-estimated and the biomass removal
plan revised to accommodate more realistic and environmental friendly
options.
Composting and
incineration are suggested as options but not discussed. The implication
being that the DOE would grant permission to undertake open burning.
Considering
the disapproval Malaysia has made of the Indonesian practice of
open burning for forest clearance in Indonesia - sometimes by Malaysia-owned
companies, it will be embarrassing for the Malaysian Government
to permit open burning at home for a Japanese funded project.
Incineration
may be difficult since 2.238 x 106 tonnes is a lot of matter to
incinerate ; it would take the proposed Kg.Bohol MSW incinerator
5.1 years to process that amount.
Since incineration
would require chipping or shredding up-front to increase surface
area, it may be possible to consider options such: as sale of wood
chips (if a buyer can be identified), and/or composting wood chips
with or without sewage sludge. These could be practical alternatives
far cheaper than incineration and far more acceptable than open
burning
The DE study
should have discussed the impacts and trade-offs that would
arise if residual biomass were:
 |
left untreated
at the bottom of the lake;
|
 |
felled
and removed by open burning;
|
 |
felled,
chipped and removed by complete burning incinerators;
|
 |
felled,
chipped with sale and residuals partially removed by composting.
|
The study should
have discussed the physical quality of the residual biomass, its conversion
processes to an equilibrium state with the environment, the release
of components into environmental media, transport routes, biological
targets and the effects and impacts of these processes and on their
targets.
The DE may be
correct in implying that open burning is the only affordable solution,
but it should at least make an attempt to identify effects, identify
targets, qualify and quantify the costs that would be externalised
and assess health risks to affected communities.
VIII. RISK ASSESSMENT
Safety risks
from construction and operations of the dam, water transfer tunnel,
etc. has been treated in a general discussion which makes no attempt
to qualify let alone quantify the risks that come from this project.
In our view the DE has failed to address the TOR on this issue.
We expect the DE to have:
 |
Identified
the components that risked failure in this project;
|
 |
Identified
the consequences of failure;
|
 |
Identified
the targets that were exposed to these consequences; and
|
 |
Identified
the costs they may have to bear.
|
Describing the
circumstances leading up to failure locally - at Ampang Pechah, or
from similar climatic areas would have been more informative than
quoting examples of historical dam failure in the US and Europe.
IX. SOCIAL IMPACTS
The socio-economic
impacts of the proposed project are indeed significant. Of particular
concern is the displacement of local communities including the Orang
Asli at Sungei Temir and the destruction of their livelihood.
While resettlement
plans and alternative income generation activities sound good on
paper, actual implementation of such plans in other dam projects
in the country are fraught with massive problems with serious grievances
among the displaced communities. Examples include the Batang Ai
Hydro-electric project in Sarawak, the Bakun Dam and the Selangor
Dam project. SAM has compiled numerous complaints from the indigenous
communites displaced by the Bakun Dam project, who now face food
shortages, loss of jobs, increased crime, alcoholism, break up of
community life, loss of their pride and dignity, with the threat
of cultural extinction. Similar problems are also seen in studies
of the Batang Ai project and other dam projects around the world.
The DE has
not taken into account these examples, which not only deal with
issues related to compensation, but which involve the impact of
such projects on the culture and lifestyle of these communities.
These are very serious considerations, which are not dealt with
in the DE and are neccesary to evaluate whether real benefits are
realised by displaced communities from such projects.
Superficial
surveys which do not provide actual details of the trade-offs the
communities have to put up with are grossly misleading and insufficient.
If the communities are given the opportunity to visit other communities
who have been displaced by other dam projects, we are convinced
that no one will agree to be displaced in the first place. By and
large, all the promises of a good life after the displacement have
remained illusory.
It is about
time that Consultants who undertake socio-ecomomic assesments and
make recommendations on paper visit actual resettlement schemes
to assess the actual impacts of such projects on local communities.
X. CONCLUSION
In the light
of the above, we submit that the DE is seriously flawed in many
respects, inadequate, misleading in parts and suffers from fundamental
defects. As it stands, the DE does not satisfy the requirements
of Section 34A(2) of the EQA and should therefore be rejected as
is provided in Section 34A(4).
Submitted by Sahabat Alam Malaysia and the Consumers' Association
of Penang
Dated: 8 November 2000.
|